Integrated Wastewater Framework

Integrated Wastewater Framework

Whitehouse, Northern Ireland

Design and construction of improvement works to existing WwTW including process plant, pipelines, building and civil engineering works. The new process comprises aeration, final settlement, sludge handling and standby generation.

Client DRD Water Service
Consulting Engineer White Young Green
Design for Biwater GRAHAM by: Ferguson & McIlveen
Value £10,900,000
Contract Period 102 weeks