Bin Mountain Wind Farm
Castlederg, Co-Tyrone
Design and construction of the civil works for the 9MW wind farm which comprises six turbines (hub height = 55 metres and rotor diameter = 72 metres), associated transformers, a permanent anemometer mast, access tracks, a site control room and substation, electrical cabling, and all ancillary works.
| Client | Bin Mountain Wind Farm NI Ltd |
|---|---|
| Consulting Engineer | Scott Wilson |
| Value | £1,593,476 |
| Contract Period | 20 Weeks |