Downpatrick Wastewater Treatment Works

Downpatrick WwTW

Downpatrick, Co-Down

Turnkey design and construct contract for upgrade works to existing treatment works in Downpatrick town.

The project included 1 anoxic tank, 1 primary settlement tank, 1 new and 2 refurbished, existing final settlement tanks, new sludge storage and handling facilities, refurbishment and extension to 2 existing storm tanks, structural repairs to existing tanks, interstage and inlet pump stations, odour control, infrastructure, and upgraded pipelines through the town, along with the refurbishment of two satellite pump stations.

Client NI Water Ltd
Consulting Engineer

McAdam Design
Design for Biwater GRAHAM by Scott Wilson

Value £9.45m
Contract Period July 2008 to April 2010