Integrated Wastewater Framework

Whitehouse WwTW

Whitehouse, Co-Antrim

Turnkey Design and Construct contract for a 100,000 P.E. WwTW on an existing works.

The project included upgrading the inlet works, 4 Lane FBDA Activated Sludge Plant, 4 Final Settlement Tanks, 2 thickened sludge storage tanks, 4 sludge buffer tanks, and 4 pumping stations, odour control, steel portal framed process buildings.

The existing works remained fully operational throughout the works.

Client DRD Water Service
Design for Biwater GRAHAM by Ferguson McIlveen (now Scott Wilson)
Consulting Engineer White Young Green
Value £13.9m
Contract Period April 2005 to September 2007