Project Overview

Client Grant Thornton

Project Value £1.8m

Expertise Interior Fit-Out

Sector Office

Timeline September 2017 to November 2017

Location Northern Ireland

Grant Thornton (Donegall Square West)

Grant Thornton banks on GRAHAM

Project summary 

Coinciding with Grant Thornton’s “exponential growth”, we delivered a high-quality £1.8m fit-out of the professional services firm’s new Belfast headquarters. Completed in just 12 weeks, our comprehensive refit of the third floor of the iconic Danske Bank building in Donegall Square West has created the platform for the accountancy giant’s ambitious future plans for the region.

The high-quality, largely open plan Grade A office accommodation features call booths and collaboration zones throughout, and includes 11 meeting rooms, a relaxed client seating area and a library.

Project Contact Kenny Gardner Operations Director

Email Kenny

September 2017

Project commenced

£1.8m

Project value

November 2017

Project completed

The solution

Delivered as planned on time and on budget, the state-of-the-art Grade A office accommodation fit-out incorporated high-calibre finishes and materials throughout.

Bespoke joinery, M&E installations, suspended metal ceilings, roof plant installations, kitchen installations and floor and wall finishes were key elements of the redevelopment programme. A priority for Grant Thornton was the installation of top of the range I.T and AV systems which would be fully flexible and adaptable to meet future advances in technology.

The existing space also contained ‘strong rooms’, inclusive of large security safes, reflecting the third floor’s former banking role. Showcasing our innovative approach, these were adapted to fit modern filing and storage systems. Merging traditional fixtures and fittings with vibrant colours and materials established an entirely fresh perspective for the offices, while unique wall coverings were erected that depicted famous Northern Ireland landmarks.

Completed in 25,199 ‘manhours’ with zero RIDDORS, the project was also notable for our sustainability performance, including 100% waste to landfill and the utilisation of timber supplied from a sustainable chain of custody source.

1 / 10

"Moving to such an iconic, city centre landmark reflects our confidence in the future, and will provide a fitting and professional environment that will help facilitate our continued expansion"

Richard Gillan Managing Partner, Grant Thornton

"In our opinion GRAHAM are a professional, well-organised contractor with an excellent team who delivered on time and to a very high standard of finish. I want to thank the team for all the hard work over the last few months. Your amazing effort is really appreciated, and the office far exceeds all our expectations"

Peter Legge Partner, Grant Thornton